ATOS Stage 2
- Projects
- ATOS Stage 2
Description
Following the successful delivery of Stage 1, ATOS requested a high-speed delivery for four additional floors (10th–13th) in Capital 6 instead of the initially planned 14th–16th floors. The project scope involved 4,000 m² across four floors, all to be completed in less than 20 days to align with the branch opening attended by the Egyptian Minister of Communications and the French Ambassador.
The works included architectural modifications, gypsum and glass partitioning, full-scale data infrastructure implementation (cabling, data points, fire-rated doors, raised floors, racks, switches), security systems, lighting upgrades, painting, furnishing all office areas, and branding across all spaces.
Project Challenges
- Sudden shift in project scope with new floor plans.
- Ultra-tight delivery timeline of under 20 working days.
- Full integration of IT, branding, furnishing, and fit-out within a high-profile public launch.



Key Requirements
Modify and redesign four floors from scratch
Build data rooms with fire-rated infrastructure
Install MEP, IT systems, and surveillance
Deliver workstations, meeting rooms, and furniture
Execute full branding and visual identity on-site
Timeline
- Start Date: April 2024
- End Date: April 2024
Project Requirements
Deliver a complete fit-out of four floors under intense time pressure, maintaining premium quality for a prestigious launch event.